CASE STUDY · COMPLIANCE AND FIRE SAFETY
Diverging owner preferences, an existing loan, fire safety obligations - one solution
$2.7M
Total program of works
154
Total lots
<40%
Self-funded
12 Mths
Works period
01 CLIENT OVERVIEW
154-lot mixed-use strata scheme in Hornsby, NSW, with an existing strata loan and urgent fire safety works to fund.
02 CHALLENGE
- Urgent fire damper works, staged over 12 months
- Existing loan with about 27 months left, to be refinanced
- Owners split between paying upfront and paying over time
03 FUNDING STRUCTURE

CLIENT TESTIMONIAL
“Firstrata provided a solution that balanced the needs of all owners.
The ability to refinance the existing loan and fund essential works in one facility, while still giving owners flexibility, made the process far simpler and allowed us to move forward efficiently.”
— Lauren J, Strata Manager
KEY OUTCOMES
- $2.7M fully funded in a single facility, covering the fire safety works and refinancing of the existing strata loan.
- Critical works started without delay, with staged drawdowns matched to the 12-month construction program.
- Existing debt streamlined, reducing administrative complexity and improving the scheme's financial position.
- Every owner given a funding choice to pay upfront or over time, resolving conflicting preferences and enabling broad agreement to proceed.